Extension of medium voltage Substation 6A in the Port of Thessaloniki

6 bw

Extension of medium voltage Substation 6A in the Port of Thessaloniki

On 20/12/2021, the Contract for the execution of the project “EXTENSION OF MEDIUM VOLTAGE SUBSTATION 6A IN THE PORT OF THESSALONIKI” was signed between ABC and “Thessaloniki Port Authority – Th.P.A. S.A.”. The project concerns the expansion of Substation 6A and installation of Substation 7 of the Container Terminal (C.T.) and in particular:

  • Excavation of cable canals with a total length of 1.33 km
  • Installation of medium voltage cables with a total length of 11.24 km along the entire length of the route
  • Installation of 1.33 km bare copper earth conductor
  • Construction of a new electrical panel and connection of the medium voltage cables to the panels of the Substation 7
  • Construction of a well on the quay, as infrastructure for the supply of the two new cranes No3 and No 4
  • Lightning protection of the Substation building and
  • Required construction works for the routing of medium voltage cables and the creation of the necessary wells.